問題 #65
The following question requires your selection of CCC/CCE Scenario 4 (2.7.50.1.1) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.
What is the cost of manufacturing labor for the piece of equipment today?

  • A. $210,000
  • B. $140,000
  • C. $105,000
  • D. $875,000

答案:B

解題說明:
Given Data:
Present-day price of equipment: $350,000
Manufacturing labor: 40% of total cost
To calculate the cost of manufacturing labor today: Manufacturing Labor Cost=40%×350,000=$140,000\text{Manufacturing Labor Cost} = 40\% \times 350,000 = \$140,000Manufacturing Labor Cost=40%×350,000=$140,000

 

問題 #66
Which of the lol owing comparisons is commonly used in forensics schedule analysis (FSA)?

  • A. Earned value vs scheduled value
  • B. Cost performance index (CPI) to schedule performance index (SPI)
  • C. As-planned vs as-built
  • D. Forensic productivity analysis

答案:C

解題說明:
Forensic Schedule Analysis (FSA) often compares the planned progress (as-planned) with the actual progress (as-built). This method helps identify variances and delays by analyzing how the actual construction compares with what was originally planned. This comparison is crucial in understanding deviations from the schedule and assessing the impact of delays.

 

問題 #67
An agricultural corporation that paid 53% in income tax wanted to build a grain elevator designed to last twenty-five (25) years at a cost of $80,000 with no salvage value. Annual income generated would be $22,500 and annual expenditures were to be $12,000.
Answer the question using a straight line depreciation and a 10% interest rate.
How much money should be set aside today to have $20,000 available eight (8) years from now if the interest rate is 6% compounded annually?

  • A. $13,515
  • B. $29,600
  • C. $12,550
  • D. $31,875

答案:C

 

問題 #68
Which of the following is NOT a type of float?

  • A. Free
  • B. Total
  • C. Negative
  • D. Open end

答案:D

解題說明:
Float, also known as "slack," refers to the amount of time that a project task can be delayed without causing a delay to subsequent tasks or the overall project completion. The types of float include:
Total Float: The amount of time a task can be delayed without delaying the project's completion date.
Negative Float: Occurs when the project is behind schedule, meaning tasks must be accelerated to meet deadlines.
Free Float: The amount of time a task can be delayed without delaying the early start of any subsequent tasks.
Open end is not recognized as a type of float. Therefore, it is the correct answer as it does not belong to this list.

 

問題 #69
The following question requires your selection of CCC/CCE Scenario 28 (3.7.50.1.7) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.
If the owner in A has a primary goal of completion within budget, the following contract types with the engineer/contractor would be best:

  • A. Engineer - cost plus, contractor cost plus
  • B. Engineer - fixed price, contractor fixed price
  • C. Engineer fixed price, contactor cost plus
  • D. Engineer - cost plus, contractor fixed price

答案:B

解題說明:
If the owner's primary goal is completion within budget, a fixed price contract for both the engineer and the contractor is the best option. This contract type ensures that the costs are controlled, and there is less risk of budget overruns since both the engineer and the contractor are incentivized to work within the agreed budget. Therefore, the correct answer is D. Engineer - fixed price, contractor fixed price.
Top of Form
Bottom of Form

 

問題 #70
......

在這個競爭激烈的IT行業中,擁有一些認證證書是可以幫助你步步高升的。很多公司升職加薪的依據就是你擁有的認證證書的含金量。AACE International CCP認證考試就是個含金量很高的考試。AACE International CCP 認證證書能滿足很多正在IT行業拼搏的人的需求。Testpdf可以為你提供AACE International CCP認證考試的針對性訓練。你可以先在網上免費下載Testpdf為你提供的關於AACE International CCP 認證考試的培訓工具的試用版和部分練習題及答案作為嘗試。

CCP套裝: https://www.testpdf.net/CCP.html

通過AACE International CCP的考試是不簡單的,選擇合適的培訓是你成功的第一步,選擇好的資訊來源是你成功的保障,而Testpdf的產品是有很好的資訊來源保障,通過對CCP考試主題的研究,我們可以知道,前三個CCP考試主題下包含的考試重點相對比較多,使用包/幀分析和AACE International CCP套裝調試工具等,最新的AACE International CCP考試是最受歡迎的認證之一,很多考生都沒有信心來獲得此認證,Testpdf保證我們最新的CCP考古題是最適合您需求和學習的題庫資料,如果你選擇了CCP考古題,快下載它吧,能100%通過IT認證考試,AACE International CCP真題 並且我們提供的練習題是和真正的考試題目很接近的,幾乎是一樣的。

以我們的軍力,劫掠這個海島花不了幾個時辰的時間,但最後的防守警戒線永遠是自己,通過AACE International CCP的考試是不簡單的,選擇合適的培訓是你成功的第一步,選擇好的資訊來源是你成功的保障,而Testpdf的產品是有很好的資訊來源保障。

最真實的CCP認證考試的學習資料

通過對CCP考試主題的研究,我們可以知道,前三個CCP考試主題下包含的考試重點相對比較多,使用包/幀分析和AACE International調試工具等,最新的AACE International CCP考試是最受歡迎的認證之一,很多考生都沒有信心來獲得此認證,Testpdf保證我們最新的CCP考古題是最適合您需求和學習的題庫資料。

如果你選擇了CCP考古題,快下載它吧,能100%通過IT認證考試。

P.S. Testpdf在Google Drive上分享了免費的、最新的CCP考試題庫:https://drive.google.com/open?id=1zPynfFkjI48IW0DK7ZsPWa6It78OWxmH